SAVANNAH, Ga. (WTOC) - The Public Service Commission has approved a contract between Georgia Power and OpenAI’s Project Camila, finalizing what officials describe as historic levels of power output after years of negotiations.
‘Strictest contract in data center history’ reached between Georgia Power and OpenAI
SAVANNAH, Ga. (WTOC) - The Public Service Commission has approved a contract between Georgia Power and OpenAI’s Project Camila, finalizing what officials describe as historic levels of power output after years of negotiations.
WTOC
Publisher
Aug 30, 2026 at 11:25 PM UTC · 2 dk okuma

Chatham County Commissioner Alicia Johnson said it is the strictest contract in data center history.
Regulatory compact
PSC Utilities Director Tom Bond said the contract departs from typical regulatory practice.
“What we’ve done here is not consistent with what they call the regulatory compact,” Bond said.
Bond said the reason involves the amount of risk both OpenAI and Georgia Power face if the operation does not proceed as planned.
“If a data center leaves or a group of data centers leave, do you have the tools to continue to protect customers?” Bond said.
Binding terms
The contract is binding. The amount of money paid and the amount of relief given to residents will remain unchanged should the project be delayed or canceled.
“Hopefully we’ll never have to decide this but if it does happen we’ll have to decide whether we’ll get Georgia Power to eat it, or we’re going to make other large-load customers pay for it,” Bond said.
OpenAI is classified as a large-load customer. Georgia Power spokesperson Joshua Peacock said the company is being treated like any other client.